The Hub

For this fit out, on behalf of M&G investments, we took an empty new build shell, close to Manchester Cathedral, and provided a full CAT A finish, including M&E package together with mezzanine access and infrastructure upgrades.

Existing structural features were incorporated to give an open, industrial design with exposed air conditioning and ventilation services. Walls were dry lined and a raised access floor installed to give the prospective tenants maximum flexibility for any future CAT B enhancements.

In addition to the main floor plate of 400m2 Contract Services undertook access core enhancements, thermal and fire protection works.

We’ve included interior designer Bluesky’s original concept design CGI for comparison….and its pretty close to the finished article!

The contract was completed to budget and within the 9 week program, for Christmas 2019.