+Well Healthcare, Meir Park, Stoke on Trent

+Well have been working to fully automate their pharmaceutical dispensing operation at the National Distribution Centre in Stoke for 3 years. 

As their construction partner, Contract Services have been retained as Principal Contractor on the phased construction of 60,000 sq ft of production and office mezzanine space.  

Works have been carried out in a live environment enabling +Well to maintain their warehousing and distribution capabilities.  In addition to installing the production mezzanine, a full revamp of the mechanical and electrical services has been undertaken.

Contract: Mezzanine Installation

Value: £3.5 million

Programme: 22 weeks